Wellesley Construction – Update #2

Construction on our Wellesley store continues to progress as planned.  Though there’s still much to do, our construction team has accomplished a lot in the past month.

  • The cement slab, which the team tore up last month in order to install plumbing, is now whole.
  • Framing (to support our interior walls) is now complete.
  • Installation of “rough” plumbing is ongoing.
  • Installation of “rough” electric is ongoing.

Wellesley - Early August 2016

Next up, we have our rough plumbing and electric inspections and the hearing for our restaurant permit (often referred to as a Common Victualler’s license).

Check back soon for more updates and follow us on snapchat (thirstjuiceco) to come with us behind the scenes on our site visits!